楼主: hkhtg090201
收起左侧

[美国] 2020,太空发射系统SLS首秀Artemis-1(原EM-1),将在KSC发射:进行方案修正

[复制链接]
 楼主| hkhtg090201 发表于 2015-4-16 06:16 | 显示全部楼层
一个重要节点:所用Orion首次焊接,5月开始。
http://www.nasaspaceflight.com/2015/04/em-1-orion-crew-module-first-weld-milestone-may/
wsl2005 发表于 2015-5-14 10:46 | 显示全部楼层
本帖最后由 wsl2005 于 2015-5-14 10:52 编辑

发射计划定在2018年11月,,,
http://www.spaceflightinsider.com/missions/human-spaceflight/full-scale-mockup-of-nasas-orion-spacecraft-completed-in-lead-up-to-2018-em-1-mission/

In Littleton, Colorado, Lockheed Martin has completed the construction of a full-scale mockup of NASA’s new crew-rated spacecraft, Orion. This Orion crew module and adapter full-scale mockup was transferred to the Orion Test Lab (OTL ) on May 13, 2015, so that it can be used to prepare Orion for its second flight into the black on Exploration Mission 1.
EM-1 is currently scheduled to take place in November of 2018 and will be the first flight of NASA’s new super heavy-lift booster, the Space Launch System or “SLS”. This will not be Orion’s first flight, however, as the spacecraft was launched atop a United Launch Alliance Delta IV Heavy booster in December of 2014.


A mockup of NASA's Orion spacecraft, which will be used to prepare for the 2018 Exploration Mission 1, has finished being constructed by Lockheed Martin.
11.jpg


wsl2005 发表于 2015-5-14 11:11 | 显示全部楼层
本帖最后由 wsl2005 于 2015-5-14 11:15 编辑

一个模拟视频截图:
http://www.space.com/19289-new-nasa-capsule-to-fly-around-moon-in-2017-animation.html#ooid=00aTZ5cDrItv6r9jqk8LLL13pcme0SfR
121.png

122.png

PS:感觉是CE5TI放大版,,,




wsl2005 发表于 2015-5-24 22:17 | 显示全部楼层
hkhtg090201 发表于 2015-4-10 11:06
立方体卫星载荷
NASA adding to list of CubeSats flying on first SLS mission   Posted on April 8, 2 ...

这些立方星中有一个NASA的Lunar Flashlight cubesat,貌似太阳光帆,其目的是把光线反射到月球陨石坑阴影处(月球手电筒),看能否找到水和冰,,
lunar-flashlight-mission.jpg

http://www.space.com/29464-cubesats-space-science-missions.html
wsl2005 发表于 2015-5-29 08:33 | 显示全部楼层
wsl2005 发表于 2015-5-24 22:17
这些立方星中有一个NASA的Lunar Flashlight cubesat,貌似太阳光帆,其目的是把光线反射到月球陨石坑阴影 ...

http://sservi.nasa.gov/articles/lunar-flashlight/

http://space.skyrocket.de/doc_sdat/lunar-flashlight.htm

一篇旧闻:
https://www.sparkfun.com/news/1522
The EM-1 mission will send an unmanned Orion space capsule around the moon and back to Earth; at some point between the Earth and the Moon the three spacecraft will be deployed and proceed on their own.
The three spacecraft have very different missions, but are based on common hardware which cuts development costs immensely. “Lunar Flashlight” will deploy an 80m2 solar sail, use the sail to maneuver itself into polar orbit around the moon, and will then slew the sail like a mirror to reflect sunlight into deep polar craters that are in permanent darkness. It is believed that these craters hold a significant amount of water ice, deposited by passing comets over billions of years. The reflected sunlight will be analyzed by onboard instruments to see what’s down there. The second mission, “NEA Scout”, will also deploy a solar sail. It will use it to slingshot past the moon, and attempt to rendezvous with a near-earth asteroid (NEA). The final mission, “BioSentinel”, will also fly by the moon, and perform long-term testing of biological samples in the high radiation of deep space. This information will be valuable to researchers planning to send humans to Mars.
wsl2005 发表于 2015-5-29 09:14 | 显示全部楼层
http://www.moreheadstate.edu/News/2015/April/MSU_s__Deep_Space_Probe__selected_by_NASA_for_Lunar_Mission/

Under this NASA NextSTEP program, Morehead State University and its partners, the Busek Company (Natick MA), NASA Goddard Spaceflight Center (GSFC in Greenbelt MD), and the Catholic University of America (CUA), will develop and build a 6U CubeSat designed to prospect for water ice and other lunar volatiles from a low-perigee lunar orbit flying only 100 km (62 miles) above the lunar surface. The Lunar IceCube will be deployed during lunar trajectory by the SLS (which will be the most powerful rocket ever built) and use an innovative RF Ion engine to achieve lunar capture and the science orbit to allow the team to make systematic measurements of lunar water features.  The science goals are to investigate the distribution of water and other volatiles, as a function of time of day, latitude, and regolith composition/mineralogy.
IceCube will include a version of the Broadband InfraRed Compact High Resolution Exploration Spectrometer (BIRCHES) instrument, developed by NASA GSFC. BIRCHES is a compact version of the successful volatile-seeking spectrometer instrument on the New Horizons mission that is currently approaching Pluto.
黑与白 发表于 2015-6-2 22:50 | 显示全部楼层
本帖最后由 黑与白 于 2015-6-2 22:54 编辑

根据NSF最新消息这次任务2018年完成后,下一次载人发射已经被推迟到了无敌的2024年,也就是说orion飞船在2024年才能第3次发射,也是第一次载人发射,我看人类飞出地球指望不上NASA了OMG
cmj9808 发表于 2015-6-2 23:40 | 显示全部楼层
黑与白 发表于 2015-6-2 22:50
根据NSF最新消息这次任务2018年完成后,下一次载人发射已经被推迟到了无敌的2024年,也就是说orion飞船在20 ...

有没有链接?我看了下SLS section,没看到相关内容
wsl2005 发表于 2015-6-19 16:47 | 显示全部楼层
据NASA网站201542日报道,美国国家航空航天局(NASA)的新一代火箭航天发射系统SLS)的首次探索任务(EM-1)将完成多项重大任务,不仅要测试SLS的性能、SLS火箭与猎户座飞船的融合度,还将利用其强大的运载能力搭载11枚小卫星,以便在低地轨道之远开展科学实验。
  首次非载人飞行试验中,SLS火箭将把猎户座飞船发射至绕月逆行轨道。11枚独立的小卫星被装配在连接猎户座飞船和SLS顶端推进级的适配器内,每枚约有一个大鞋盒大小。适配器圆环上的阀门采用的是弹簧结构,没有采用烟火装置。
  这些小卫星以高效多能为其设计宗旨。总质量不超过14千克,不需要耗费火箭的额外推力,降低了深空探索科研的成本。
  逃离地球引力约10分钟后,猎户座飞船将与其服务舱分离,此后猎户座飞船将继续向月球进发。当猎户座飞船飞至安全距离之外,就可以根据任务需要在不同的时间部署小行星了。
  该载荷的项目负责人和工程师将制定有针对性的任务要求,以确保载荷搭载的安全性。NASA的多个机构也为这11个载荷空位发出了意见征集书,目前有三个提议入选,分别是 近地小行星(NEA)侦察Near-Earth Asteroid Scout)、月球闪光灯Lunar Flashlight)和生物哨兵BioSentinel)。
  近地小行星侦察将使用太阳帆推进技术,飞越一枚规模较小的小行星,对其拍照并进行观测。这将加深当前人们对小行星环境的理解并为将来航天员探索小行星获取关键信息。
  月球闪光灯将在月球表面搜寻资源丰富的地点,这些资源一旦被分解成有用的分子,即可在未来的探索中用于制作材料、推进燃料、氧气和水。
  生物哨兵将使用酵母探测、测量和比较深空辐射对活体微生物的影响。(尉艳娟 温熙越 编译)
 楼主| hkhtg090201 发表于 2015-6-22 07:09 | 显示全部楼层
本帖最后由 hkhtg090201 于 2015-6-22 07:10 编辑

ESA的服务舱将在“pLum Brook"测试,一直持续到明年。乘员舱在到KSC之前,也要在"紫溪?”测试。

These test structures will be put through their paces deep into next year, prior to heading to Lockheed Martin’s facility in Sunnyvale, California for additional testing. Should all the testing prove to be successful, the EM-1 Service Module will be flown into KSC in January of 2017 for integration with the EM-1 Orion inside the Operations & Checkout (O&C) building, following a similar path to the EFT-1 flow. However, rather than heading out to mating with its launch vehicle, the entire EM-1 spacecraft will then be shipped to Plum Brook Station for environmental testing that qualifies the vehicle for flight, and only then will it be returned to Kennedy for launch processing. That will mark the launch processing flow, as the day approaches for the mating of the Orion stack with the SLS inside the Vehicle Assembly Building (VAB).

http://www.nasaspaceflight.com/2015/06/plum-brook-orion-service-module-testing/
 楼主| hkhtg090201 发表于 2015-6-22 07:16 | 显示全部楼层
pLum BrooK 梅溪
cmj9808 发表于 2015-7-23 21:32 | 显示全部楼层
首射搭载的两个太阳帆Near Earth Asteroid Scout和Lunar Flashlight cubesat,分别执行小行星1991VG 飞掠和进入月球极轨,后者还要利用太阳帆作为反光镜照亮月球极区阴影,很有趣的方案

http://spacenews.com/nasa-developing-solar-sailing-cubesats-for-inaugural-sls-launch/
黑与白 发表于 2015-7-23 21:42 | 显示全部楼层
cmj9808 发表于 2015-7-23 21:32
首射搭载的两个太阳帆Near Earth Asteroid Scout和Lunar Flashlight cubesat,分别执行小行星1991VG 飞掠和 ...

类似苏联原来发那人造月亮?

点评

有点像小号的  发表于 2015-7-23 21:52
wsl2005 发表于 2015-7-29 09:26 | 显示全部楼层
wsl2005 发表于 2015-7-29 09:41 | 显示全部楼层
Lunar IceCube的任务是在月球找水,近月点高度100公里。其开发费用为790万美元,卫星重量1.33公斤,体积一升,验证卫星已经在LEO进行过试验。

http://www.examiner.com/article/lunar-icecube-to-examine-water-on-the-moon-with-nasa-grant


 楼主| hkhtg090201 发表于 2015-10-15 11:17 | 显示全部楼层
用于EM-1的 固推的 部分硬件开始加工(processing)


As reported by Orbital ATK, “Production has already started for the EM-1 test flight.

“Motor hardware began processing June of this year in Utah. Booster small parts processing will begin at KSC within the next few weeks.”

As such, Orbital ATK is on track to support not only the first test flight of SLS in three years, but also the continued operation of SLS into the 2030s and beyond.


http://www.nasaspaceflight.com/2015/10/orbital-atk-booster-production-sls-maiden-flight/

黑与白 发表于 2015-10-27 13:22 | 显示全部楼层
最新消息显示,本次任务已经推迟到2018年11月
wsl2005 发表于 2015-11-11 14:15 | 显示全部楼层
黑与白 发表于 2015-10-27 13:22
最新消息显示,本次任务已经推迟到2018年11月

42楼5月份消息就是这个时间,,

ESA提供的基于ATV货运飞船开发的Orion服务舱已经运抵美国,准备测试。
http://www.esa.int/Our_Activities/Human_Spaceflight/Orion_s_European_module_ready_for_testing
European_Service_Module_副本.jpg

Orion_ESM_structural_test_model_副本.jpg


 楼主| hkhtg090201 发表于 2015-11-16 15:38 | 显示全部楼层
EM-1之路:SLS初次飞行硬件(开发)里程碑概述
日期
硬件类型:事件
Road to EM-1: NASA outlines hardware milestones to SLS debut flight
November 11, 2015 by Chris Gebhardt
    距离发射3年之际,NASA已经开发了一个综合里程碑生产流程,勾勒出所有必须硬件的处理里程碑,帮助稳固发射路径,包括发射场…
   With approximately three years to go before the inaugural flight of the Space Launch System rocket, NASA has developed the integrated mission milestone processing flow for the EM-1 flight. The flow, which outlines all the necessary hardware processing milestones to a 2018 inaugural flight of SLS, helps solidify SLSs path toward launch, including the pad processing timeline once the first SLS rocket is fully integrated.
Overview:概览
Over the course of its development, the various components of what will be the SLS launch vehicle have taken shape and undergone testing across the United States and the European community.
  但是,这些测试和活动涉及(分散于)四处的单个组件…
But those tests and activities have revolved around single components of the SLS rocket as contractor agencies focused on development of their portion of the SLS vehicle while NASA itself has worked toward and through the Critical Design Review (CDR) - completed this year - to solidify the integrated version of the new Heavy Left Vehicle (HLV).
随着CDR的完成,迎来这些组件的第一次整合…. 开发转入高速档期…
With the CDR now complete, work to bring the constituent components of SLS together into the first integrated configuration of the vehicle begins in earnest, as flight production kicks into high gear this year with the build of flight hardware toward an aim of launching the first SLS mission - Exploration Mission 1 (EM-1) - in the late 2018 timeframe.
… 每个将最终组成这个重型火箭的组件 - 以及需要支持这个大型火箭的地面系统 - 仍然…
But even as SLS heads toward an integrated configuration, each of the major components of what will eventually be the HLV - as well as the ground hardware needed to support the massive rocket -  still have individual paths toward completion before they all converge at the Kennedy Space Center in Florida, inside the Vehicle Assembly Building (VAB), for stacking operations for EM-1.
1. LAS:发射中止系统
根据综合任务里程碑概要,以及….
According to the Integrated Mission Milestone Summary and associated L2 flow schedule information for EM-1 from the Exploration Systems Development (ESD) office, fabrication of the Launch Abort System (LAS) and ogive began in October 2015.
2015/10/1
LAS:开始加工(筹备?)
Build-up of the Jettison Motor (JM) is slated to start in February 2016 followed by the start of production on the Attitude Control Motor (ACM) mass simulator in March 2016.
2016/2/3
LAS:抛弃马达(JM)开始形成
2016/3/1
LAS:姿态控制马达(ACM)大型模拟器开建
Construction of the Abort Motor (AM) mass simulator will follow in September 2016 as well.
2016/9/1
LAS:中止马达(AM)大型模拟器建造
After more than a year and a half of production, the JM will be delivered to the Kennedy Space Center in May 2017.
2017/5/1
LAS:经过一年多的生产,JM交付到KSC
This will be followed by the deliveries of the ACM mass simulator to KSC in August 2017 and of the AM mass simulator to KSC in October 2017.
2017/8/1
LAS:ACM大型模拟器交付到KSC
2017/10/1
LAS:AM大型模拟器交付到KSC
Finally, the LAS and ogive itself will be delivered to the Launch Abort System Facility (LASF) at KSC in February 2018.
2018/2/1
LAS:(LAS和ogive)交付KSC的LASF
2. Crew Module/Orion:猎户座乘员舱
For the Crew Module (CM), also known as Orion, the first flight weld of the CM for the EM-1 mission occurred in September 2015, with primary structure completion slated for later this month.
2015/9/1
CM:第一焊
2015/11/30
CM:初始基础构架完成
By the end of January/beginning of February 2016, the CM structure will be completed at the Michoud Assembly Facility (MAF) in Louisiana.
2016/2/1
CM:(总体)构架完成@MAF(马苏德组装车间)
到KSC装配
It will then be delivered to the Operations & Checkout (O&C) building at the Kennedy Space Center (KSC) for outfitting tasks.
2016/3/1
CM:递送到KSC(O&C)进行舾装.
Following the CMs delivery to the O&C, a pressurization proof test will be conducted in April 2016 followed by CM propellant proof leak testing in September 2016.
2016/4/15
CM:压力检验测试 @O&C
2016/9/1
CM:推进检验密封测试  @O&C
3. European Service Module:欧洲服务舱
期间,在意大利都灵已经建造了欧洲服务舱… …
Meanwhile, the European Space Agency (ESA) has been constructing the European Service Module (ESM) for the EM-1 flight at its Turino, Italy, facility.
Structural assembly for the ESM was completed in September of this year ahead of transportation of the ESM STA to NASAs Plum Brook facility in Sandusky, Ohio.
2015/9/1
ESM:结构组装完成 @ 德国??
2015/11/13
ESM:运到美国NASA的梅溪车间(俄亥俄州)
  所有ESM组件的预备整合期待在2016年3月完成,然后进入一个长期的系列测试,这指定在2017年1月达成。
Pre-integration of all ESM components is expected to be completed by March 2016 before the ESM enters a prolonged series of tests, which are slated to wrap in January 2017.
2016/3/10
ESM:所有组件的预备整合完成
2017/1/10
ESM:一个长期系列测试完成
After these tests, the entire ESM will be delivered to the O&C facility at the Kennedy Space Center in March 2017.
2017/3/10
ESM:递送到KSC(O&C)
4. Command and Service Module:指令与服务舱
… 两者配接在一起构成一个命令与服务舱(CSM)
Once the CM and ESM are together in the O&C building, the two will be mated together to form the Command and Service Module (CSM).
2017/5/1
CSM:=CM+ESM:2者配接完成@O&C
Once this integration is complete, the CSM will be transported back to Plum Brook in Ohio for T-Vac testing.
2017/7/1
CSM:回到梅溪进行T-Vac(热真空?)测试
2017/9/20
CSM:完成T-Vac测试  @梅溪
Upon completion of that T-Vac testing, the CSM will be returned to the O&C in October 2017 before being handed over to ground operations in January 2018 and moved to the Multi-Payload Processing Facility (MPPF).
2017/10/10
CSM:从梅溪又返回KSC(O&C)
2018/1/2
CSM:交付到地面操作并移动到MPPF
在MPPF待3个月,将到LASF…
Following three months in the MPPF, the CSM will be taken to the LASF at the Kennedy Space Center in March 2018 where it will be mated to the LAS.
2018/3/30
CSM:交付到LASF(中止系统车间),与LAS配接。
The combined LAS and CSM will then be moved to the Vehicle Assembly Building in April 2018 ahead of stacking operations with the SLS Core Stage and Interim Cryogenic Propulsion Stage (ICPS).
2018/4/1
CSM+LAS:到VAB与火箭主体堆接
5. Interim Cryogenic Propulsion Stage:过渡型低温推进级
随着ULAs的ICPS结构测试体完成,ULA安排在2016年1月开始生产第一个飞行单元ICPS
With United Launch Alliances (ULAs) ICPS Structural Test Article (STA) completed, ULA is slated to begin production of the first flight unit ICPS in January 2016.
2016/1/10
ICPS:开始建造(正式的)飞行体
A new estimated completion date of the flight unit ICPS is January 2017.
2017/1/10
ICPS:飞行单元体估计建造完成
随着完成…,这个ICPS将运到KSC,在那里他将递交给地面操作在2018年一月,并移动进入MPPF。
Following completion at ULAs Decatur, Alabama, facility, the ICPS will be shipped to the Kennedy Space Center in Florida where it will be handed off to ground operations in January 2018 and moved into the MPPF.
2017/12/10
ICPS:运到KSC,…
2018/1/2
ICPS:交付地面操作并转移到MPPF
在MPPF大约停留4个月
Following an approximate four month stay in the MPPF, the ICPS will be moved to the Vehicle Assembly Building in April 2018 for stacking and integration operations with the Core Stage of the SLS and the CMS/LAS.
2018/4/25
ICPS:转移到VAB,与核心级等堆接
6. Core Stage and Engines:核心级与发动机
… … 核心级发动机的开发测试指定年底结束,
As MAF continues to work through acceptance of the Vertical Assembly Center, development testing for the Core Stage engines is slated to be completed by the end of the year, with the four flight engines for the EM-1 mission due for delivery to MAF between April and September 2016.
2015/12/25
核心级:MAF内的制造工具-垂直装配中心(VAC)准备好
2015/12/25
RS-25等核心发动机:发动机开发测试完毕。
2016/4/1
RS-25:第一台发动机交付MAF
2016/9/1
RS-25:第四台发动机交付MAF
At MAF, manufacturing of the STA for the Core Stage is set to be completed by December 2016.
2016/12/10
核心级:STA(结构测试体)完成制造 @MAF
This will be followed by assembly of the flight engine section in December 2016 and completion of assembly manufacturing of the flight intertank section of the Core Stage in January 2017.
2016/12/20
RS-25部件(适配器?):开始组装到火箭核心级
2017/1/10
核心级:飞行级箱间段:完成组装加工
  在2017年2月底/3月初的时候,整个核心级组装体 将被连接在一起,(这些)在2017年8月之前结束。
The entire Core Stage assembly will then be joined together in late-February/early-March 2017 before the Core Stage is finished at MAF by August 2017.
2017/3/1
核心段+发动机等:整体开始组装@MAF
2017/8/1
核心段+发动机等:整体组装完成@MAF
… 在B2 测试台,热点火日期仍然等待决定。
At this point, the Core Stage will be transported in a one day trip by barge to the Stennis Space Center (SSC) in Mississippi where it will be hoisted onto the B2 test stand for a hot fire run at a date that is still to be determined.
2017/11/1
核心段整体:运到Stennis的B2测试台
2017/12/18
核心段整体:Stennis热点火测试(日期为大概)
Following completion of this hot fire test at SSC, the Core Stage will be loaded back onto the barge for the week-long trip around the Florida peninsula for delivery to the Kennedy Space Center and handoff to ground operations at the spaceport in January 2018.
2018/1/1
核心段整体:回到KSC,交付给地面操作
The Core Stage will then be moved into the VAB where it will undergo acceptance and final checkout operations before mating operations to the twin Solid Rocket Boosters.
2018/3/1
核心段整体:进入VAB,准备与SRB对接。
7. Boosters:(5段固体)助推器
With the propellant void issue and the QM-1 (Qualification Motor -1) test behind them, Orbital ATK has begun production on the flight motor segments that will comprise the twin, five-segment Solid Rocket Boosters (SRBs) for SLSs first mission.
Production on the flight motor segments began in July 2015 and will run through February/March 2017.
2015/7/1
SRBs:飞行马达段开始生产
2017/3/1
SRBs:飞行用马达段完成生产
While those flight motor segments are in production, Orbital ATK will conduct the final qualification test firing of the five-segment SRB, the QM-2 test, in March 2016.
2016/3/15
SRBs:QM-2测试点火
Once flight motor segment build operations are complete at Orbital ATKs Utah facility, the 10 propellant segments for SLSs maiden flight SRBs will ship to the Kennedy Space Center in 2017 and 2018.
2017/9/1
SRBs:飞行产品准备启运到KSC
Under the current Integrated Mission Milestone Summary, the Forward and Center SRB segments will arrive at the Kennedy Space Center in September and October 2017.
2017/10/1
SRBs:前中段运到KSC
This will be followed by the delivery of the Aft Skirts in November/December 2017 and then the Aft segments of the SRBs in late-January/early-February 2018.
2017/12/1
SRBs:后裙段运到KSC
2018/2/1
SRBs:后段运到KSC
Finally, the Forward segments are currently slated to arrive at the Kennedy Space Center in early March 2018.
2018/3/1
SRBs:前段运到KSC
8. Ground:地面系统
But it isnt just the various hardware elements of the SLS vehicle itself that are still undergoing preparations for the EM-1 mission.
All of the ground support structures at the Kennedy Space Center and Johnson Space Center are also progressing toward readiness for SLSs inaugural flight.
In October 2015, the Ground System Development and Operations (GSDO) team kicked off their own CDR for all of the ground support equipment and operations that will be needed to support the SLS Program.
2015/10/1
Ground:GSDO-CDR开球
That GSDO CDR is expected to run through December 2015.
2015/12/30
Ground:GSDO-CDR完成
At the Kennedy Space Center, structural modifications to the Mobile Launcher (ML) were completed in the autumn of 2015.
2015/9/1
Ground:ML结构修改完成 @KSC
Moreover, the GSDO team will take the Spaceport Command and Control System (SCCS) version 3.0 for Hazardous Operations Control and Communication through validation operations by April 2016.
2016/4/1
Ground:SCCS V3.0通过确认操作
Version 4.0 of the SCCS will be verified and completed by March 2017.
2017/3/1
Ground:SCCS V4.0验收完成
Prior to SCCS version 4.0, all VAB platform modification for SLS will be completed by December 2016 with Umbilical installation onto the ML accomplished by January 2017.
2016/12/12
Ground:所有VAB平台变更完成
2017/1/1
Ground:脐带安装到ML
Following umbilical installation and VAB platform modification, the ML and VAB integration systems will be verified and validated by April 2017 with the VAB deemed ready for SLS operations by May 2017.
2017/4/1
Ground:ML和VAB整合系统核实与验收
2017/5/1
Ground:VAB准备完毕,迎接SLS操作
Just prior to VAB completion, pad 39Bs flame trench and deflector modifications will be completed in April 2017, with ML/Pad integration verification and validation operations wrapping in late-September/early-October 2017.
2017/4/1
Groundad39B:导焰沟和偏导器修改完成
2017/10/2
Ground:ML/Pad验收确认操作完成
Pad 39B will be ready in January 2018 with the Mission Control Center at JSC ready in February 2018.
2018/1/1
Groundad39B准备完毕
2018/2/1
Ground:JSC-MCC准备完毕
9. SLS stacking, integration, and pad ops:堆栈,整合,以及发射台操作
随着所有的SLS构成部分准备好,NASA将实施该机构自1979年以来还没有做过的重要事情:在VAB中堆砌和整合一个全新的运载火箭。
With all of SLSs constituent elements ready, NASA will realize something that hasnt happened for the agency since 1979: the stacking and integration of a completely new launch vehicle inside the VAB.
Following the VAB stacking SAR/ORR (Safety Analysis Report/Operational Readiness Review) in July 2017, the ML will be moved into VAB High Bay 3 for final preparations for the commencement of stacking operations.
2017/7/3
堆:VAB stacking SAR/ORR(安全分析报告/操作准备评审)
如同航天飞机,SLS的堆砌从固体助推器的组装开始
Like Shuttle, stacking of the SLS vehicle will begin with the build-up of the SRBs.
2018年3月,起飞日期大约6个月之前
In March 2018, approximately six months prior to the targeted lift off date, the SRB segments will begin moving to the VAB transfer aisle where theyll be connected to cranes and lifted over the transom and stacked onto the ML surface.
2018/3/30
堆:SRB段:移动到VAB转运过道,连接到起重吊车,升到横梁,堆砌到ML表面上。
这标志着2011年后VAB内的首次出现运载火箭的堆砌操作… …
This will mark the first time since 2011 that stacking operations for a launch vehicle have occurred inside the VAB.
According to the Integrating Mission Milestone Summary, stacking operations of the twin SRBs will last approximately two months, from the beginning of March to the end of April 2018.
2018/4/30
堆:SRB:完成2个SRB的连接。
*Grab your 2016 NASASpaceFlight.com Calendar!*
Following SRB stacking, the HEO (Human Exploration and Operations) and Exploration Systems Development (ESD) divisions will convene their Integration Review to finalize all integration operations of the SLS.
2018/5/9
整合:2个部门的整合评审
一旦HEO/ESD整合评审完成,这个大型核心级将提升到横梁上,并且下降放置到两个SRBs之间 - 一定程度上类似于航天飞机… ...堆装操作。
Once the HEO/ESD Integration Review is complete, the massive Core Stage will be lifted over the transom and lowered between the two SRBs - in a manner similar to how the External Tank was lowered between the SRBs during Space Shuttle stacking operations.
Core Stage mate to the SRBs and the MLs umbilicals will occur in early-May 2018 prior to a late-May/early-June Partial Modal Test of the combined SRB-Core Stage launch vehicle propulsion elements.
2018/5/5
堆:Core Stage mate to the SRBs (核心级配接固推)
2018/6/2
堆:SRB-Core结合体运载火箭推进元素偏部模态试验.
This will be followed in mid-June 2018 by the mating of the ICPS and Orion on top of the Core Stage.
2018/6/10
堆:最后配接 (SRBs+Core)+(ICPS+CSM)
Once ICPS and Orion mating operations are complete, a Full Modal Test of the SLS integrated launch vehicle will occur in late-June.
2018/6/20
SLS:完整的SLS运载火箭全模态测试
Also occurring in late-June will be the Agency Flight Readiness Review (FRR).
2018/6/30
SLS:局级FRR
Following this Full Modal Test and the Agency FRR, SLS will spend the entire month of July inside the VAB undergoing integrated vehicle checkouts before conducting the first of two rollouts to launch pad 39B at the beginning of August.
2018/7/28
SLS:花费整个7月进行综合运载器效验
在当前的整合里程碑概要下,SLS将在发射台花费大约一个月经受一个干彩排测试,接下来一个湿彩排,以使该发射团队评估他们的倒计时操作 以及 确认发射台和运载器性能参数有效,然后提交到EM-1发射活动。
2018/8/1
SLS: 首次RollOut To Pad39B 为彩排
Under the current Integrated Mission Milestone Summary, SLS will spend approximately one month at launch pad 39B undergoing a dry rehearsal test followed by a wet dress rehearsal to allow the launch teams to evaluate their countdown operations and validate pad and vehicle performance parameters prior to committing to the EM-1 launch campaign.
2018/8/2
SLS:在39B花费一个月进行彩排,先是干彩排…
2018/8/20
SLS:接下来是湿彩排...。
Following the wet dress rehearsal in mid- to late-August, the SLS vehicle will be returned to the VAB in late-August for final closeouts and ordnance installation operations.
2018/8/30
SLS:返回VAB
The performance of final closeout operations and Ordnance installation inside the VAB is a marked difference from Shuttle operations, where those operations took place during the often month-long stay at the pad.
2018/9/1
SLS:军械安装
Once closeout and Ordnance installation is complete, SLS will be rolled back out to pad 39B in September for a final, short volley of pad operations before launch on the EM-1 mission - currently slated by November 2018.
2018/9/28
SLS:正式RollOut To Pad39B
2018/11/10
SLS发射
Assuming a September 2018 launch, the Post Flight Assessment and Review of the EM-1 mission will occur in December 2018, followed by Post Flight Crew Module Transport and Deservicing in January 2019.
2018/12/1
EM-1飞行后评估与审查
2019/1/1
EM-1飞行后乘员舱运输与维修
(Images: Via Philip Sloss, NASA and L2 - including SLS renders from L2 artist Nathan Koga - The full gallery of Nathans (SpaceX Dragon to MCT, SLS, Commercial Crew and more) L2 images can be *found here*)
(To join L2, click here: http://www.nasaspaceflight.com/l2/)
黑与白 发表于 2015-11-16 15:41 | 显示全部楼层

辛苦                                          
您需要登录后才可以回帖 登录 | 注册会员

本版积分规则

QQ|小黑屋|航空航天港 ( 豫ICP备12024513号-1 )

GMT+8, 2019-9-16 20:59 , Processed in 0.405601 second(s), 21 queries , Gzip On.

技术支持:飞腾网络

© 2001-2018

豫公网安备 41019702002513号

快速回复 返回顶部 返回列表